1. Does the Open Permit Match the Property's Actual Work?
An open permit does not necessarily establish a building-code violation. The White Plains Department of Building provides an Open Permit Status Request form to document the status of permitted work. The buyer should determine whether the permit records reflect the property's actual condition.
Match the Permit to the Property
Compare the permit number, work description, approved plans, and inspection history with the property's condition. Finished construction may lack a final inspection or differ from the approved plans. A contractor's statement that work is complete does not establish municipal approval.
Identify the Reported Permit Status
The City's form identifies five conditions:
| Permit Status | What to Verify |
|---|---|
| Work not begun | Whether construction remains planned |
| Work underway | Expected completion date |
| Work delayed | Reason for the delay |
| Work finished | Final inspection or compliance evidence |
| Work will not proceed | Whether cancellation was accepted |
Work not begun
- What to VerifyWhether construction remains planned
Work underway
- What to VerifyExpected completion date
Work delayed
- What to VerifyReason for the delay
Work finished
- What to VerifyFinal inspection or compliance evidence
Work will not proceed
- What to VerifyWhether cancellation was accepted
The applicant, contractor, or owner reports the status. Submitting the form does not itself close the permit. The reported status does not establish that the City has closed the permit.
2. What Must Happen before an Open Permit Is Closed?

Completed construction may require a final inspection, while discontinued work may require an accepted cancellation request. The City determines the remaining requirements based on the permit and work performed.
Arrange the Final Inspection
The Open Permit Status Request calls for proof of final inspection and/or a Certificate of Compliance for completed work. The responsible party must arrange access and coordinate the inspection with the assigned Code Enforcement Officer. The buyer should confirm whether the inspection has occurred or remains outstanding.
The form warns that failure to make arrangements within 30 days after receiving the City's correspondence may lead to legal action. This is not a general real estate closing deadline.
Confirm Approval or Cancellation
Request written confirmation of the City's determination, including an applicable inspection record, certificate, or accepted cancellation. If the City identifies unfinished or noncompliant work, determine what corrections and further inspections are required.
A Certificate of Occupancy addresses authorized occupancy, while a Certificate of Compliance may document specific improvements. Neither necessarily covers unrelated work.
3. Who Must Resolve an Open Permit before Closing?
The City determines municipal compliance requirements, while the purchase contract governs which party must resolve an outstanding permit issue. The buyer should review those obligations before agreeing to proceed.
Compare Municipal Findings with the Contract
Review the purchase agreement, riders, and written promises concerning alterations or required approvals. These documents help establish whether the seller agreed to deliver the property with completed inspections or specified municipal approvals.
If the seller agreed to obtain final approval, compare that obligation with the City's findings. Without an express provision, the buyer's rights depend on the remaining contract terms and applicable law.
Check the Lender's Closing Requirements
A mortgage lender may require proof of municipal approval before releasing funds. Identify the specific closing condition and required documents. A repair credit does not necessarily satisfy a lender's requirement for final approval.
For broader transaction procedures, see the real estate closing review in New Rochelle.
4. Can Closing Proceed with an Open Permit?
Closing may proceed if the contract, financing terms, and applicable requirements permit an agreed arrangement. Any solution must account for outstanding municipal obligations and identify who will complete the necessary work.
Evaluate an Extension or Escrow
An extension may allow time for corrective work. An escrow may secure an outstanding obligation if the parties, lender, and title insurer approve.
The written agreement should identify the required work, responsible party, deadline, completion evidence, and consequences of nonperformance. Escrow terms must also establish the amount and release conditions.
Neither arrangement eliminates the City's approval requirements.
Review the Closing Deadline before Alleging Default
A stated closing date does not necessarily make time of the essence. An express contract provision or a valid subsequent notice may establish a binding deadline.
A subsequent notice generally must set a clear deadline, allow reasonable time to perform, and warn that failure to close will constitute default.
Before refusing to close or seeking the deposit's return, the buyer must review the contract, permit findings, and notices. An unresolved permit alone does not establish a right to terminate.
5. Reviewing Open Permits before a White Plains Closing
Before closing, a buyer should determine whether the City requires additional work, whether the seller must complete it, and whether the lender will accept a proposed resolution.
SJKP LLP can evaluate open-permit disputes and closing arrangements through its real estate transfer practice.