Commercial Construction Contract: Who Pays When Work Stops



Commercial construction contracts allocate cost overruns, delay risk, and defect liability between parties in ways most signatories do not fully read.

A commercial construction project involves dozens of contracts layered on top of each other, from the owner-contractor agreement to subcontracts, supplier agreements, and bonding arrangements. Each layer allocates specific risks, and the provisions that determine who bears those risks are negotiated before the project begins. A project that runs over budget, finishes late, or produces defective work generates disputes whose outcomes are already largely determined by what the contract says, not by who is morally at fault. An attorney who handles commercial construction contract matters can identify the provisions that create the greatest exposure before they are signed rather than after a dispute makes them the focus of litigation.

Commercial construction contracts are governed by state contract law and, for federal public works projects, by the Miller Act, 40 U.S.C. § 3131, which requires general contractors to obtain payment and performance bonds on all federal construction projects valued above $150,000. State Little Miller Acts impose similar bonding requirements for state and local public projects at varying thresholds.

Contents


1. What a Commercial Construction Contract Must Contain to Protect Each Party


A commercial construction contract is not a single document. It is a package of documents that includes the agreement form, the general conditions, the special conditions, the project specifications, and the drawings, and each component governs a different aspect of the project relationship.

The American Institute of Architects publishes the most widely used standard form commercial construction contracts in the United States. The AIA A101 stipulated sum agreement, the AIA A102 cost-plus agreement, and the AIA A133 guaranteed maximum price agreement each use the AIA A201 general conditions as their operating framework. These standard forms represent decades of negotiation between owner and contractor interests and provide a reasonable starting point, but they are regularly modified by owner-specific supplementary conditions that shift risk back toward contractors in ways the AIA's balanced framework was designed to avoid.

The scope of work definition is the most commercially significant provision in any construction contract. A scope that is defined by reference to drawings and specifications that contain conflicts, ambiguities, or omissions creates disputes from the first week of construction. Under the Spearin Doctrine, established in United States v. Spearin, 248 U.S. 132 (1918), an owner who provides plans and specifications to a contractor implicitly warrants their adequacy. A contractor who follows defective plans and specifications is entitled to additional compensation for the resulting additional work, regardless of what the contract's change order procedure requires.



How the Contract Type Determines Who Bears Cost Overruns and Risk


The pricing structure of a commercial construction contract determines which party absorbs cost increases when materials, labor, or site conditions turn out to cost more than anticipated, and the choice of contract type is one of the most consequential decisions made before a project begins.

A lump sum or stipulated sum contract fixes the contractor's price for the defined scope of work. The contractor bears all cost risk: if materials cost more than estimated, if labor productivity is lower than anticipated, or if a condition not addressed in the contract increases the work required, the contractor absorbs the additional cost unless a compensable change order is approved. Owners prefer lump sum contracts for well-defined scopes because they provide cost certainty.

A cost-plus contract pays the contractor its actual costs plus a fee for overhead and profit. The owner bears all cost risk and gains unlimited visibility into project costs but no certainty about the final price. A guaranteed maximum price contract, or GMP, adds a ceiling to a cost-plus arrangement: the contractor bears costs above the GMP, but any savings below it may be shared with the owner under a shared savings clause. An attorney who handles construction contracts and commercial project negotiations can evaluate which contract type fits the project's scope definition, the owner's risk tolerance, and the contractor's capacity to absorb cost volatility.

Contract TypeWho Bears Cost RiskPrice Certainty for OwnerBest for
Lump sum / stipulated sumContractor bears all overrunsHigh, fixed priceWell-defined scope, competitive bid
Cost-plus with feeOwner bears all actual costsNoneFast-track projects, undefined scope
Guaranteed maximum priceOwner to GMP, contractor aboveCapped maximumComplex scope, some design uncertainty
Unit priceEach unit priced, quantity risk on ownerPartialQuantity-variable work like earthwork


2. How Commercial Construction Contract Payment Provisions Create Disputes


Payment disputes are the single most common source of construction litigation, and they almost always trace back to contract provisions that the parties negotiated, or failed to negotiate, at the outset of the project.

Progress payment applications are submitted by the contractor on a defined schedule, typically monthly, and must be approved by the owner or the owner's representative before payment is released. The contract specifies the time within which the owner must pay after approval, and most state prompt payment statutes impose statutory interest and, in some cases, attorneys' fees when payment is withheld beyond the contractual and statutory deadlines. A contractor who receives a partial payment or a payment withholding must understand both the contractual basis for the withholding and the applicable prompt payment statute before deciding whether to stop work.

Retainage is the percentage of each progress payment that the owner withholds until project completion or until specific milestones are reached. Standard retainage rates of 5 to 10 percent create a significant cash flow burden for contractors and subcontractors. Many states have enacted retainage reduction statutes that require owners to reduce retainage after a defined percentage of work is complete, typically 50 percent, but these statutes apply primarily to public projects and may not apply to private commercial contracts. An attorney who handles construction payment disputes can evaluate whether the retainage withholding complies with the applicable statutes and contract terms.



Why Pay-If-Paid Clauses and Pay-When-Paid Clauses Produce the Most Contractor Claims


Pay-if-paid clauses in subcontracts attempt to make the general contractor's obligation to pay the subcontractor contingent on the general contractor receiving payment from the owner, effectively shifting the owner's non-payment risk down the contract chain to the subcontractor.

Courts have split significantly on whether pay-if-paid clauses are enforceable. States that enforce them treat the clause as a valid allocation of risk that the subcontractor agreed to by signing the contract. States that refuse to enforce them hold that a subcontractor cannot waive the statutory right to mechanic's lien protection by contract, and that pay-if-paid clauses that eliminate the subcontractor's right to payment for completed work violate public policy. California is among the states that have limited the enforceability of pay-if-paid clauses in construction contracts.

Pay-when-paid clauses are less aggressive. They condition the timing of the general contractor's payment obligation on the general contractor receiving payment, but they do not eliminate the obligation entirely if the owner fails to pay. Courts generally enforce pay-when-paid clauses as reasonable timing provisions rather than conditions precedent to payment. The distinction between the two types of clauses is often a single phrase, and a subcontractor who does not understand which type of clause their contract contains cannot accurately assess the payment risk they have accepted. An attorney who handles subcontracts and commercial construction disputes can analyze the payment clause language and advise on whether the clause is enforceable as written in the applicable jurisdiction.


Payment delays on commercial construction projects compound through the subcontract chain faster than most owners anticipate. A general contractor who holds payment from subcontractors while awaiting owner payment creates a liquidity crisis for trades whose profit margins cannot sustain 90-day payment cycles. The lien filing deadlines that protect unpaid contractors run from dates tied to last work performed or materials furnished, not from the date payment was demanded. Those deadlines pass while payment disputes are unresolved.



3. What Happens When a Commercial Construction Contract Is Breached or Terminated


A commercial construction contract can be terminated for cause when one party materially breaches its obligations, or terminated for convenience when the owner chooses to end the project without cause, and the financial consequences of each type of termination are materially different.

Termination for cause by the owner occurs when the contractor fails to maintain the required pace of work, uses non-conforming materials, fails to pay subcontractors, or otherwise materially defaults. The contract typically requires the owner to provide written notice of default and a cure period before termination becomes effective. An owner who terminates for cause before establishing a valid default, or before providing the required notice and cure period, may convert what appeared to be a legitimate termination for cause into a wrongful termination that gives the contractor a claim for lost profits on the remaining work.

Termination for convenience clauses allow the owner to stop the project without any default by the contractor, in exchange for paying the contractor its costs incurred to date, a reasonable overhead allocation, and in most standard form contracts, a percentage of the fee on the terminated portion of the work. Termination for convenience clauses are standard in government contracts and increasingly common in private commercial contracts, but contractors who have invested in mobilization, long-lead material procurement, and project staffing and then face a convenience termination often find that the contractual payment falls well short of their actual loss.



How Mechanics Liens Protect Unpaid Contractors after a Default


A mechanic's lien is a statutory security interest that attaches to real property when contractors, subcontractors, or material suppliers who contributed to the improvement of that property are not paid for their work.

The mechanic's lien statutes of each state create a process through which an unpaid party can record a claim against the property and, if the claim is not paid, enforce it through a foreclosure action that forces the sale of the property to satisfy the lien. This lien right is powerful because it encumbers the owner's most valuable asset and creates a title defect that prevents the owner from refinancing or selling the property until the lien is released or bonded over.

Mechanic's lien rights are subject to strict procedural requirements that vary significantly by state. Preliminary notice requirements, which in many states must be served on the owner and general contractor within a specified period after first furnishing labor or materials, are a prerequisite to lien rights in most states. Missing a preliminary notice deadline eliminates lien rights regardless of the merits of the underlying payment claim. Lien recording deadlines, dispute periods, and foreclosure filing deadlines are all statutory and jurisdictional in nature. An attorney who handles mechanics liens and construction litigation matters can determine the applicable notice and recording deadlines for each project and advise on compliance before any deadline becomes imminent.



How Delay Claims Are Handled under Construction Contracts and When They Fail


Delay claims are the most complex category of commercial construction contract disputes because they require proof of which party caused the delay, what the impact of that delay was on the project schedule, and which contract provisions limit or eliminate recovery for the delay.

Delays are classified as excusable when caused by events beyond either party's control, such as unusually severe weather, acts of God, or government-ordered shutdowns, and compensable when caused by the owner's actions or failures, such as late design decisions, differing site conditions, or owner-directed changes. Excusable delays entitle the contractor to a time extension but not additional compensation. Compensable delays entitle the contractor to both a time extension and additional compensation for the extended general conditions costs, escalation, and lost productivity caused by the delay.

No-damage-for-delay clauses, found in many owner-drafted commercial construction contracts, purport to limit the contractor's recovery for owner-caused delays to a time extension only, eliminating the right to additional compensation regardless of the owner's fault. Courts in most states enforce these clauses with limited exceptions, including fraud, active interference by the owner, delays of such unreasonable duration as to amount to abandonment, and delays not contemplated by the parties at the time of contracting. An attorney who handles construction dispute and delay claim matters can evaluate whether a specific delay falls within one of the recognized exceptions to no-damage-for-delay enforcement and structure the claim accordingly.

Delay claims on commercial construction projects are document-intensive. The contemporaneous daily logs, weather records, correspondence, schedule updates, and owner response records created during the delay period are the evidentiary foundation of any claim. A contractor who fails to document the delay's causes and impacts as they occur, or who fails to provide timely notice of delay as the contract requires, may have valid delay damages that are procedurally barred by the time the claim is presented. The notice requirement runs from the date the delay begins, not from the date the project is complete.



4. Frequently Asked Questions about Commercial Construction Contracts


Property developers, general contractors, subcontractors, and project owners approaching a commercial construction dispute or contract negotiation for the first time share a consistent set of questions about what their contracts actually say and what their rights are when projects go wrong. The most common of those questions are answered here.



What Is a Commercial Construction Contract and What Does It Cover?


A commercial construction contract is a legally binding agreement between an owner and a contractor, or between a general contractor and subcontractors, that defines the scope of work, the contract price, the schedule, the payment terms, the allocation of risks including delays and cost overruns, the warranty obligations, and the dispute resolution procedures for a commercial construction project. It governs every aspect of the project relationship from mobilization through final payment and post-completion warranty obligations.



What Is the Difference between a Lump Sum and a Cost-Plus Contract?


A lump sum contract fixes the contractor's price for the defined scope of work, and the contractor bears all cost overruns above that price. A cost-plus contract pays the contractor its actual costs plus a fee, with the owner bearing all cost risk and having no certainty about the final price. A guaranteed maximum price contract combines elements of both, setting a ceiling on the cost-plus arrangement so that costs above the GMP fall on the contractor while savings below it may be shared with the owner.



What Is a Mechanic'S Lien and How Does a Contractor File One?


? A mechanic's lien is a statutory security interest that attaches to real property when a contractor, subcontractor, or material supplier is not paid for work or materials that improved the property. To preserve lien rights, the claimant must typically serve preliminary notices on the owner and general contractor shortly after first furnishing labor or materials, record the lien with the county recorder within a defined period after completing work, and file a foreclosure action to enforce the lien within the statute's enforcement deadline. Each state's requirements differ, and missing any deadline permanently eliminates lien rights for that project.



What Does the Miller Act Require on Federal Construction Projects?


The Miller Act, 40 U.S.C. § 3131, requires that any general contractor on a federal construction project valued above $150,000 obtain both a payment bond and a performance bond before beginning work. The payment bond guarantees that subcontractors and material suppliers will be paid even if the general contractor fails to pay them. The performance bond guarantees that the project will be completed according to the contract if the general contractor defaults. Subcontractors who are not paid on federal projects can bring a claim directly against the payment bond without needing to file a mechanic's lien, because federal property is not subject to mechanics liens.



What Is a No-Damage-for-Delay Clause and Is It Enforceable?


A no-damage-for-delay clause limits a contractor's recovery for owner-caused delays to a time extension only, eliminating the right to additional compensation for extended general conditions, escalation, and lost productivity regardless of who caused the delay. Most states enforce these clauses with limited exceptions, including delays caused by the owner's active interference, fraud, delays not contemplated by the parties when the contract was signed, and delays so unreasonably long as to constitute abandonment. An attorney who handles construction defect litigation and construction contract disputes can evaluate whether a specific delay falls within one of these exceptions.



What Rights Does a Subcontractor Have When the General Contractor Does Not Pay?


An unpaid subcontractor has several remedies depending on the contract terms and the applicable state law. Mechanic's lien rights against the property are available on private projects if the required notices and deadlines are met. Payment bond claims are available on public projects where a payment bond was required. Direct claims against the owner under trust fund statutes, available in some states, allow the subcontractor to recover construction funds that the owner paid to the general contractor but that the general contractor diverted rather than passing through to the subcontractor. An attorney who handles construction and engineering law matters can evaluate which remedy is available, whether the procedural prerequisites have been met, and which approach is most likely to result in payment.


30 Dec, 2025


La información proporcionada en este artículo es únicamente con fines informativos generales y no constituye asesoramiento legal. Los resultados anteriores no garantizan un resultado similar. La lectura o el uso del contenido de este artículo no crea una relación abogado-cliente con nuestro despacho. Para asesoramiento sobre su situación específica, consulte a un abogado calificado autorizado en su jurisdicción.
Ciertos contenidos informativos en este sitio web pueden utilizar herramientas de redacción asistidas por tecnología y están sujetos a revisión por parte de un abogado.

Áreas de práctica relacionadas


Reservar una consulta
Online
Phone