[Construction Payment Claim Lawsuit Favorable Judgment Case] Favorable Judgment in a Construction Payment Claim Lawsuit, Recovering the Construction Payment and Delay Damages
The client who came to Daeryun for a construction payment claim lawsuit had not been paid the construction payment by the defendant.
1. The Client Who Came to File a Construction Payment Claim Lawsuit
The client who visited Daeryun to file a construction payment claim lawsuit requested assistance to claim the unpaid construction payment from the defendant, who was the building owner.
The Reason for Filing the Construction Payment Claim Lawsuit
The client who came to file a construction payment claim lawsuit was a contractor who had entered into a construction contract with the defendant, the building owner.
After completing the work on the new building, the client requested the construction payment from the defendant.
The defendant asked for a little more time, and the client gave the defendant time.
However, the building owner changed, and the client grew anxious and contacted the defendant, but the defendant gave no response.
The client then requested Daeryun's assistance in proceeding with a construction payment claim lawsuit against the defendant.
Statutes Related to the Construction Payment Claim Lawsuit
■ Statutes Related to the Construction Payment Claim Lawsuit
Payment Claim Lawsuit (Price of Goods, Service Fees, etc.)
▶Civil Act, Article 568 (Effect of Sale)
(1) The seller shall transfer to the buyer the right that is the object of the sale, and the buyer shall pay the price to the seller.
(2) The mutual obligations under the preceding paragraph shall be performed simultaneously, unless there is a special agreement or custom.
▶Civil Act, Article 163 (Short-Term Extinctive Prescription of Three Years)
The extinctive prescription of the following claims is completed if they are not exercised for three years.
1. Claims for interest, support, salary, rent, or other money or goods to be paid for a period fixed within one year
2. Claims of physicians, midwives, nurses, and pharmacists relating to treatment, labor, and dispensing
3. Claims relating to construction of contractors, engineers, and others engaged in the design or supervision of construction
4. Claims of attorneys, patent attorneys, notaries, certified public accountants, and judicial scriveners for the return of documents kept in the course of their duties
5. Claims of attorneys, patent attorneys, notaries, certified public accountants, and judicial scriveners relating to their duties
6. The price of products and goods sold by producers and merchants
7. Claims relating to the work of artisans and manufacturers
▶Commercial Act, Article 64 (Commercial Prescription)
The extinctive prescription of a claim arising from a commercial activity is completed if it is not exercised for five years, unless otherwise provided in this Act. However, where another statute provides for a prescription shorter than this, that provision applies.
2. Assistance for the Construction Payment Claim Lawsuit
To obtain a favorable judgment in the construction payment claim lawsuit, the Daeryun Law Firm attorney built a strategy for the client with professional knowledge and know-how.
The Point That a Contract Exists Between the Client and the Defendant
The client and the defendant in the construction payment claim lawsuit prepared a construction contract before proceeding with the work.
A construction contract is legally effective, and its obligations must be performed.
The Daeryun attorney argued the point that there was evidence of a construction contract between the client and the defendant.
The Point That the Client Repeatedly Sent Reminders Before the Construction Payment Claim Lawsuit
Before the construction payment claim lawsuit, the client made efforts to recover the construction payment from the defendant.
The client contacted the defendant regularly and asked about the construction payment.
The Daeryun attorney argued that the client had made efforts to recover the construction payment and should recover the construction payment along with delay damages through the construction payment claim lawsuit.
The Point That the Defendant Made Excuses and Avoided the Client's Contact
The defendant in the construction payment claim lawsuit intentionally made excuses and did not pay the construction payment to the client.
As a result, the client has still not received the construction payment, up to the time of this construction payment claim lawsuit.
The Daeryun attorney emphasized the point that the defendant had made excuses in order to avoid paying the construction payment to the client.
3. The Client Who Obtained a Favorable Judgment in the Construction Payment Claim Lawsuit
The client who had been preparing the construction payment claim lawsuit obtained a favorable judgment through the Daeryun attorney's assistance and was able to recover the construction payment along with delay damages.
If You Are Preparing a Construction Payment Claim Lawsuit
The reason the client was able to obtain a favorable judgment in the construction payment claim lawsuit was the Daeryun attorney's professional assistance.
Daeryun Law Firm assists clients with a systematic structure and the litigation experience of attorneys who focus on the field.
If you are concerned about a matter similar to the client above, you may consult with a Daeryun Law Firm attorney who focuses on construction payment claim lawsuits.
![[해결사례]탬플릿 기반 복사 [공사대금청구소송 승소사례] 공사대금청구소송에서 승소하여 공사대금과 지연손해금까지 받아내](/_next/image?url=https%3A%2F%2Fd1tgonli21s4df.cloudfront.net%2Fupload%2Fseo%2Fsuccess%2F20240611055142284.webp&w=828&q=100)
This content is based on actual cases handled by Daeryun Law LLC and has been partially adapted. All copyrights belong to Daeryun Law LLC.
Unauthorized reproduction, copying or distribution may result in legal action under applicable laws.
Construction payment: Want a faster, more detailed consultation?
Consult aspecialized attorney
Related Information
Explore legal information related to this case.
Gathering Evidence and Methods for Claiming Damages in a Key Money Lawsuit
The Procedure for a Civil Lawsuit for Severance Pay and Preparing Evidence
Methods for Resolving Nonpayment of Construction Payment and the Procedure for a Construction Payment Claim Lawsuit
Daeryun's Key Strengths

Litigation strategy using Daeryun's own AI & IT technology
More than 240 key members
1,200+ cases handled per month
* 2025년 월평균 기준
Complies with Korean Bar Association Advertising Regulations Article 4 (1)
more strengths
Book a legal
consultation with an attorney
All consultations are reviewed by a specialized attorney first,
so they are conducted by appointment only.
Phone consultation
1800-7905
Available 24 hours a day, 365 days a year


Online consultation
We provide tailored
legal services for our clients.

Chat consultation
KakaoTalk channel
Daeryun Law LLC Attorneys
Key Case Studies
View moreRelated Practice Areas
View moreConsult in other languages
Popular Columns
View moreAssessing the Requirements for Filing a Claim for Damages and Methods of Preparing Evidence

On What Standards Is Compensation for Emotional Distress Determined? Examining the Calculation of Amounts and How to Claim

A Step-by-Step Guide to Civil Trial Procedure and Estimating the Required Time

Compensation Standards in Civil Defamation Litigation and Methods of Gathering Evidence

How to File for Provisional Attachment and Provisional Injunction: What Are the Specific Criteria for Determining the Requirements?

Previous
[Cheonan Lawsuit Against the Adulterous Partner Attorney Favorable Judgment Case] Cheonan Lawsuit Against the Adulterous Partner Attorney Obtains Tens of Millions of Won in Consolation Money From the Adulterous Partner
Next
[Jeonju Damages Attorney Case] Daeryun Jeonju Damages Attorney, Claim for Damages for a Random Assault
View listDo you have more questions?