EPC Contract Dispute | Successful Claim for Additional Equipment Construction Costs
The client who consulted the corporate attorney over an EPC contract dispute requested assistance in resolving a dispute over construction costs arising from the ordering party's request for additional work.
1. How the EPC Contract Dispute Arose

An EPC contract is commonly concluded in large-scale industrial projects and has a structure under which the contractor performs design, procurement, and construction on a turnkey basis.
This case is one in which, in an arbitration where a claim for additional construction costs arising from the owner's request was at issue, the client prevailed with Daeryun's assistance.
Refusal to Pay the Additional Construction Costs
This is the account of a client who came to Daeryun after a dispute arose over an EPC contract.
The client, a construction contractor, had entered into an EPC contract for a domestic industrial complex construction project and was carrying out the supply and installation of equipment.
In the course of the construction, unforeseen structural constraints and conditions differing from the design came to light, making additional reinforcement work unavoidable.
In addition, the supplementation and additional installation of new equipment were required for safety management purposes, and unforeseen work beyond the original plan inevitably proceeded.
As a result, the client incurred substantial unforeseen costs, but the ordering party refused to pay the additional construction costs on the basis of a comprehensive liability clause in the contract.
Concerned about substantial losses arising from an unreasonable interpretation of the contract, the client came to Daeryun and requested assistance.
2. EPC Contracts: Responding to Delayed Payment
In an EPC contract, the most important obligation of the owner is payment of the contract price.
If the owner fails to pay on time, the contractor or builder bears a significant burden in carrying out the work and managing its finances.
To prevent this and to protect the contractor's rights, the contract generally includes the following mechanisms.
▶ Imposition of interest for delayed payment
Accordingly, the contractor should include in the contract a provision that allows recovery of the procurement costs or financing interest incurred during the period of delay.
▶ Right to suspend the work
The contractor should therefore secure the right to suspend the work temporarily if nonpayment continues for a certain period.
▶ Termination of the contract and compensation for loss
In practice, the owner sometimes uses its superior position to omit such provisions protecting the contractor's reasonable rights.
When entering into an EPC contract, therefore, it is important for the contractor to set out clearly the provisions on delayed payment, suspension of the work, and termination and compensation for loss, so as to protect its rights in the event of a dispute.
3. EPC Contract Dispute: Assistance Provided

The key issues in this EPC contract dispute were whether the comprehensive liability clause applied to the additional construction and design changes, how to prevent the loss caused by the owner's refusal to pay, and how to prove the necessity and unavoidability of the additional construction.
The client incurred a considerable cost burden due to unforeseen pipe reinforcement and the additional installation of safety devices, but the owner refused to pay the additional costs, relying on the comprehensive liability clause in the contract.
In this situation, strategic assistance was needed to protect the client's rights and to have a reasonable claim for payment recognized.
Contract Interpretation and Analysis of Issues
The attorney closely reviewed the EPC contract and the design materials to analyze whether the comprehensive liability clause applied even to the additional construction work.
The attorney re-examined contract provisions that could be interpreted unfavorably in a realistic and reasonable direction and, using on-site construction reports, records of design changes, and the like, was able to clearly prove the unavoidability of the additional construction work and the costs incurred due to unforeseen work.
Presenting evidence capable of proving the unavoidability of such additional construction work in a systematic manner, the attorney argued the client's legitimate claim for payment.
Collecting Evidence and Proving the Need for Additional Construction
The attorney systematically collected and analyzed the on-site construction reports and design change materials prepared by the client.
Through these materials, the attorney proved the necessity of the additional construction that arose unavoidably due to on-site conditions, and clearly established that it was work the client could not have foreseen.
Review of Contract Terms and Strategic Arguments
The corporate attorney closely reviewed the design change approval procedure, the payment conditions, and the like under the EPC contract and established a strategy to protect the client's rights.
On this basis, the attorney prepared a logical argument and an arbitration strategy to obtain recognition of the payment for the additional construction costs.
In addition, by organically connecting the contract and the on-site evidence, the attorney persuasively presented to the arbitration that the client's rights should be duly protected.
4. EPC Contract Dispute Result: “Favorable Judgment”
Through the corporate attorney's strategic assistance and systematic submission of evidence, the client's argument was accepted.
Accordingly, the client was able to be fully compensated for the additional costs incurred and secured the rights that the contractor could legitimately assert.
If a Dispute Arises Concerning an EPC Contract

In complex disputes between companies, such as those arising from EPC contracts, various legal issues, including contract interpretation and the analysis of evidence, arise at the same time.
In such situations, the assistance of an experienced corporate attorney plays an important role in helping the company manage the dispute process in an organized manner and secure its rights in a stable way.
Drawing on its experience with various EPC contract cases and practical knowledge across industries, the firm anticipates the risks a company faces in advance and establishes strategies to protect its rights.
In addition, depending on the matter, the firm cooperates with experts in each field to provide comprehensive and practical assistance, focusing on minimizing the client's risk.
If a dispute related to an EPC contract arises and legal assistance is needed, please feel free to reach out to a 🔗corporate attorney for assistance.
This content is based on actual cases handled by Daeryun Law LLC and has been partially adapted. All copyrights belong to Daeryun Law LLC.
Unauthorized reproduction, copying or distribution may result in legal action under applicable laws.
EPC contract dispute: Want a faster, more detailed consultation?
Consult aspecialized attorney
Related Information
Explore legal information related to this case.
Villa Rental Fraud: Procedures for Recovering the Deposit and Legal Responses When Harm Occurs
Renewable Energy Procurement Methods and Cost Issues to Confirm Before a PPA
Procedures and Response Methods for Recovering a Deposit and Down Payment after Contract Fraud
Daeryun's Key Strengths

Litigation strategy using Daeryun's own AI & IT technology
More than 240 key members
1,200+ cases handled per month
* 2025년 월평균 기준
Complies with Korean Bar Association Advertising Regulations Article 4 (1)
more strengths
Book a legal
consultation with an attorney
All consultations are reviewed by a specialized attorney first,
so they are conducted by appointment only.
Phone consultation
1800-7905
Available 24 hours a day, 365 days a year


Online consultation
We provide tailored
legal services for our clients.

Chat consultation
KakaoTalk channel
Daeryun Law LLC Attorneys
Related Members
View more
Kuk Il KIM
T. 070-5117-2950
Experience as chief prosecutor of Seoul Central District Prosecutors' Office and head of Goyang Branch of Uijeongbu District Prosecutors' Office

JungKyu Park
T. 070-7510-2014
Senior Judge, Ansan Branch, Suwon District Court, Supreme Court Trial Researcher, Judge Experience
Related Practice Areas
View moreConsult in other languages
Popular Columns
View moreHow to Register a Quasi-Investment Advisory Business, and Points to Note When Providing Stock Tips

Copyright Infringement: Severity of Punishment, Damages, and Response Methods

The Meaning of Corporate Rehabilitation Proceedings, the Measures Involved, and Points Requiring Caution

The Effect of a Non-Disclosure Agreement, Liability for Breach, and Key Points to Know When Drafting One

Compliance Obligations Under the Fair Transactions in Franchise Business Act and Cases of Violation

Previous
Assistance by a Quasi-Rape Attorney | Representing the Victim of Quasi-Imitative Rape to Obtain Imprisonment for the Perpetrator
Next
Violation of the Foreign Trade Act | Reduced Sentence Achieved Through the Appellate Response to the Foreign Trade Act Violation Charge
View listDo you have more questions?