Page title background (PC version)Page title background (mobile version)

Deals & Cases

Construction payment

Construction Payment | Claim for Construction Payment Against a Construction Company, 12 Million Won Granted

The client, who sought legal assistance in a dispute over the payment of construction costs, had concluded a construction contract and completed the work but had not been paid the agreed construction payment.

CONTENTS
  • 1. How the Construction Payment Dispute Arose
    • - The Client's Account
  • 2. Key Legal Issues in a Construction Payment Claim
    • - The Attorney's Assistance in the Construction Payment Lawsuit
  • 3. The Result of the Assistance in the Construction Payment Lawsuit
    • - Explanation of the Concept of Construction Payment
    • - Procedure for Resolving a Construction Payment Dispute
    • - Documents Required When Filing a Construction Payment Lawsuit
    • - Why the Assistance of an Attorney Is Important

1. How the Construction Payment Dispute Arose

The client, who sought assistance after not being paid the construction costs, had repeatedly requested payment after completing the work, but the opposing company raised issues with certain portions of the work and avoided its responsibility.

The client concluded that the matter could no longer be resolved alone and decided to proceed with legal action with the assistance of an attorney experienced in construction payment disputes, and so came to Daeryun Law Firm.

The Client's Account

How the Construction Payment Dispute Arose

The client concluded a contract for the construction of a particular facility with the opposing party, a corporation, and carried out the work in accordance with the terms of the contract.

The construction amount was set at a total of 13 million won, and the client completed all of the work within the agreed scope.

However, after the work was completed, the opposing company refused to pay the full construction amount, citing reasons such as “there are problems with certain portions of the work” and “additional supplementation is needed.”

The client faithfully responded to site inspections and requests for supplementation, and although the construction was substantially in a condition that posed no impediment to use, the opposing company delayed payment without any clear grounds.

During this process, the client had secured sufficient materials to prove that the work had been completed but found it difficult to determine how to respond legally, and so requested the assistance of an attorney.

2. Key Legal Issues in a Construction Payment Claim

The most important issues in a construction payment dispute are ① whether the work was completed in accordance with the terms of the contract and ② when the obligation to pay arose.

The opposing company attempted to reduce the amount or refuse payment by asserting certain defects or deficiencies, but the attorney determined that the key issues in this case were whether a material defect existed and whether the work could be used.

In practice, even where minor defects exist or additional supplementation is required, an important standard of judgment is that if the work is in a condition capable of achieving the purpose of the contract, the full construction payment, or a substantial portion of it, must be paid.

The Attorney's Assistance in the Construction Payment Lawsuit

To provide assistance in the construction payment lawsuit, the attorney prepared the following strategy.

1. Organizing the Contract Terms and Scope of Work

The attorney first reviewed the construction contract, the estimate, and the detailed work breakdown to organize the agreed scope of work and the amount.

Through this, the attorney distinguished whether the “unperformed work” alleged by the opposing company was in fact an essential part of the work under the contract.

2. Proving the Actual Performance of the Work

To prove that the work performed by the client conformed to the terms of the contract, the attorney comprehensively organized the following items and proved that the work had been substantially completed.

  • Photographs before and after construction
  • On-site work records
  • Records of materials used
  • Status of use after completion of the work

3. Constructing a Rebuttal to the Reduction Argument

The opposing company refused to pay the full amount on the ground that some supplementation was needed, but the attorney constructed a rebuttal centered on the following points.

  • That the matter in question was not a material defect
  • That there was no impediment whatsoever to the main purpose of the work
  • That even if a defect existed, it could not serve as a ground for nonpayment of the full amount

As a result, the attorney argued before the court that the full construction payment, or at least a substantial portion of it, had to be paid.

3. The Result of the Assistance in the Construction Payment Lawsuit

The court accepted the attorney's arguments and rendered a judgment ordering the opposing company to pay the client a total of 12 million won.

A small amount was reduced in consideration of the need for some minor supplementation, but the client was able to recover most of the construction payment and to resolve, through legal means, the long-standing problem of nonpayment.

Through this, the client was able to conclude the matter without further dispute and to continue normal business operations.

Explanation of the Concept of Construction Payment

Construction payment refers to the money that a party who has performed construction work under a contract for work or a subcontract is to be paid in return.

In general, when the work is completed in accordance with the terms of the contract or reaches a condition in which it can be used and enjoyed, the obligation to pay the construction payment arises.

In practice, it frequently occurs that, even though the work has actually been performed, the orderer or the prime contractor delays or refuses payment of the construction payment by citing reasons such as alleged defects, delayed inspection, or incomplete internal settlement.

In such cases, the claim for construction payment leads to a legal issue in which the terms of the contract, the scope of the work, whether performance occurred, and whether a defect exists are comprehensively assessed.

Procedure for Resolving a Construction Payment Dispute

A construction payment dispute typically proceeds through the following stages.

  • Completion of the work or arrival at the performance stage

Performance of most or all of the scope of work agreed under the contract

  • Request for payment of the construction payment

Issuance of a tax invoice, dispatch of a payment request, and the like

  • Nonpayment or assertion of a reduction

Assertion of the need for defect correction or supplementation, incomplete inspection, and the like

  • Preliminary response such as certified mail

Clarification of the fact of completion of the work and the payment obligation

  • Filing of the construction payment lawsuit

Claim made taking into account, where necessary, the possibility of a partial reduction

  • The court's determination

Determination of whether the work was performed, the degree of any defect, and the scope of any reduction

Documents Required When Filing a Construction Payment Lawsuit

When preparing a construction payment lawsuit, it is important to organize the following materials systematically.

Category

Required Documents

Purpose of Use

Contractual relationship

Construction contract, subcontract

Confirmation of the scope, amount, and payment terms of the work

Content of the work

Estimate, work breakdown

Proof of the agreed scope of work

Evidence of performance

Photographs before and after construction, work records

Proof of the fact that the work was actually performed

Cost documentation

Records of material purchases, labor cost data

Reinforcement of the substance of the performance of the work

Payment claim

Tax invoice, payment request

Proof of the fact that payment was requested

Course of the dispute

Text messages, emails, certified mail

Organization of the circumstances of nonpayment

The more sufficiently these materials are prepared, the more clearly the fact of completion of the work and the obligation to pay the construction payment can be proved, which may also have a positive effect on the speed and outcome of the proceedings.

Why the Assistance of an Attorney Is Important

Why the Assistance of a Construction Payment Attorney Is Important

A construction payment dispute is not a question of “whether the work was done or not” but rather an area in which the terms of the contract, the scope of the work, whether a defect exists, and the possibility of a reduction in the payment are assessed in combination.

Where the opposing party is a corporation, there are not a few cases in which payment is delayed on the ground of internal approval or avoidance of responsibility, so a response that structurally organizes the fact of completion of the work and the legal issues from the initial stage is very important.

If you are experiencing difficulties due to nonpayment of construction costs, we recommend that you submit a 🔗legal consultation reservation and then, through a professional review, accurately assess the possibility of recovery and establish a response strategy.

공사대금 | 건설회사 상대 공사대금 청구, 1,200만 원 인용

This content is based on actual case studies of Daeryun Law LLC with some adaptations, and the copyright belongs to our firm.
Unauthorized reproduction, duplication, or distribution and other copyright infringements may result in legal action under applicable laws.

Related Information
Background

Daeryun's Key Strengths

Daeryun's exclusive AI · IT
litigation strategies
Over 260
key members
1,200+ cases
handled monthly

* January 2026 Bar Association Transit Permit Issuance Criteria

*Complies with Korean Bar Association Advertising Regulations Article 4 Paragraph 1

Attorney
Legal consultation booking

All consultations are conducted by specialized lawyers after reviewing the case. It is carried out on a reservation basis to ensure a professional process.We encourage you to make an early reservation for consultation, and request adherence to the scheduled time. We will do our best to provide a satisfying consultation.

Phone
consultation 1800-7905

Available 24/7, 365 days
for consultation requests

Phone booking

KakaoTalk
consultation

KakaoTalk channel

Daeryun Law Firm Attorneys

KakaoTalk booking

Online
consultation

We provide tailored
legal services.

Online booking
Quick Menu

KakaoTalk