Page title background (PC version)Page title background (mobile version)

Practice Areas

Construction Payment Lawsuit

A construction payment lawsuit is a civil lawsuit in which, under a construction contract concluded between the owner and the contractor, where the owner fails to pay the price, the contractor brings a claim to recover the unpaid construction costs.

CONTENTS
  • 1. Construction Payment Lawsuit | Definition and Limitation Period for Claims
    • - Limitation Period for Claims
  • 2. Construction Payment Lawsuit | Tips for Drafting the Complaint
    • - Key Required Entries in the Complaint
    • - Drafting the Purport of the Claim
    • - Drafting the Cause of Action
    • - Preparing Supporting Evidence
    • - List of Attached Documents
  • 3. Construction Payment Lawsuit | Litigation Procedure and Finality of Judgment
    • - Filing and Service of the Complaint
    • - Submission of the Answer and Briefs
    • - Submission of Evidence and Examination of Evidence
    • - Hearing Date for Oral Argument and Concentrated Evidence Examination Date
    • - Pronouncement and Finality of Judgment
    • - The Procedure at a Glance
  • 4. Construction Payment Lawsuit | Method of Compulsory Execution
    • - What Is Compulsory Execution
    • - Summary of Required Documents
  • 5. Construction Payment Lawsuit | Checklist
    • - Contractor (Plaintiff) Response Checklist
    • - Owner (Defendant) Defense Checklist
    • - Construction Specialist Attorney Assistance System

1. Construction Payment Lawsuit | Definition and Limitation Period for Claims

A construction payment lawsuit is a civil lawsuit in which the contractor brings a claim to the court when the owner fails to pay the price due under a construction contract.

Here, the construction payment refers to the consideration that the contractor is to receive after the work has been completed in whole or in part, under the construction contract concluded between the owner and the contractor.

A construction payment claim lawsuit is not a simple civil claim dispute; because it requires proving the content of contract performance, the assessment of the degree of completion, and the conditions for payment, professional legal handling is required.

Limitation Period for Claims

Calculating the Limitation Period for a Construction Payment Lawsuit Claim

Under Article 163, Item 3 of the Civil Act, a construction payment claim is subject to a short three-year extinctive prescription.


That is, if the contractor does not make a legal claim within three years from the date the work was completed or the date the construction payment could be claimed, the right is extinguished.

Points to Note

∙ Starting point of the prescription : the payment due date or the date of completion of the work

To interrupt the prescription of the claim, measures such as sending a certified mail (content-certified mail), filing an application for a payment order, or filing a lawsuit are required

2. Construction Payment Lawsuit | Tips for Drafting the Complaint

Construction Payment Lawsuit Tips for Drafting the Complaint Practice Area

To file a construction payment lawsuit, it is important to properly meet the form and content of the complaint.


In particular, clearly stating the purport of the claim and the cause of action, and thoroughly preparing the supporting evidence, are what increase the likelihood that the claim will be upheld.

Key Required Entries in the Complaint

Item

Description

Identification of the Parties

Clearly state the names, business names, and addresses of the plaintiff and defendant

Identification of the Representative

Include the name and address if there is a representative

Contact Information

Telephone number, fax number, email, etc.

Purport of the Claim

State concisely and clearly the amount claimed and whether interest is claimed

Cause of Action

Draft based on supporting evidence such as the construction contract, completion of the work, and the fact of nonpayment

Identification of Attached Documents

Specify the evidentiary documents attached and the items

Date of Drafting

The date on which the complaint is drafted

Name of the Court

Accurately state the court with jurisdiction

Signature of the Drafter

Signature or seal required

Drafting the Purport of the Claim

The purport of the claim is the core that contains the conclusion of the lawsuit, and it must clearly reveal what determination the plaintiff seeks from the court.

Example of the Purport of the Claim

The defendant shall pay to the plaintiff a construction payment of KRW X0,000,000, together with an amount calculated at the rate of 5% per annum from XX XX, 20XX until the date of pronouncement of the judgment in this case, and 12% per annum from the following day until the date of full payment.

In this manner, the amount, interest rate, and period must be drafted specifically.

Furthermore, even if the judge determines that there is an obligation to pay KRW 50 million, if the plaintiff seeks payment of KRW 10 million in the purport of the claim, the judgment will order payment of KRW 10 million.

Therefore, the purport of the claim must be stated accurately.

Drafting the Cause of Action

The cause of action is the part that explains in detail the legal grounds and the factual circumstances on which the plaintiff bases the claim.

It must be drafted clearly in accordance with the Five Ws and One H (when, where, who, what, how, why).

Example of the Cause of Action

1. On XX XX, 20XX, the plaintiff concluded a construction contract with the defendant for the new construction of the ○○ building, and completed the work on XX XX of the same year.

2. The total construction payment was set at KRW X0,000,000, and the defendant agreed to pay the amount by XX XX, 20XX.

3. However, the defendant has not paid the above amount to this day, and the plaintiff therefore brings this lawsuit.

Preparing Supporting Evidence

In a construction payment claim lawsuit, the documents capable of proving the actual performance of the work and the fact of nonpayment are the core.

Key Supporting Materials

∙ Construction contract or works contract

∙ Estimate and statement of material purchases

∙ Construction design drawings and specifications

∙ Statement of work progress and statement of the degree of completion

∙ Certificate of completion of the work and certificate of delivery of the building

∙ Appraisal report (an appraisal may be requested if necessary)

The above materials are organized and submitted in the form of Plaintiff's Exhibit No. 1, Plaintiff's Exhibit No. 2, and so on, and when copies are submitted, a statement that they are identical to the originals must be entered.

List of Attached Documents

The documents that must be submitted together with the complaint are as follows.

∙ Certificate of corporate registration or certificate of family relations (to prove authority to represent)

∙ Power of attorney for litigation and application for permission to act as litigation representative

∙ Receipt for payment of stamp duty and service fees (may be omitted in the case of electronic submission)

∙ Duplicate of the complaint (at least one copy in the case of paper submission)

Since the complaint may be returned if attached documents are missing, it must be carefully checked in advance.

3. Construction Payment Lawsuit | Litigation Procedure and Finality of Judgment

Daeryun LLC's Assistance in Construction Payment Lawsuits

A construction payment lawsuit begins with the filing of the complaint and goes through numerous legal procedures until the judgment becomes final.

The following are the representative stages experienced in the actual litigation process.

Filing and Service of the Complaint

A lawsuit begins with the filing of the complaint.

After examining the submitted complaint, the court, if there are no defects, serves a ‘duplicate of the complaint’ on the defendant.


If the defendant does not respond even after receiving the complaint, the likelihood of a judgment for the plaintiff increases through a ‘judgment without oral argument.’

Submission of the Answer and Briefs

The defendant must submit an answer ordinarily within 30 days from the date of service of the complaint.

In addition, both parties may submit briefs to the court before trial to organize their arguments and evidence.

Document Name

Description

Answer

The defendant rebuts or partially admits the plaintiff's arguments

Brief

A summary organizing the evidence and arguments

List of Evidence

A table organizing the supporting evidence to be submitted

Submission of Evidence and Examination of Evidence

In civil litigation, the burden of assertion and proof lies with the parties, so proof is very important.

There are various types of evidence, including documentary evidence, witnesses, appraisal, inspection, inquiry into facts, and transcripts.

Type of Evidence

Content and Characteristics

Documentary Evidence

Documentary materials such as contracts, tax invoices, and transaction statements

Witness Examination

Having third parties such as construction-related persons or cooperating companies appear in court to give testimony

Inquiry into Facts

Requesting materials from third parties such as government offices and companies in the name of the court

Order to Submit Documents

Requesting that documents held by the other party be compulsorily submitted to the court

Hearing Date for Oral Argument and Concentrated Evidence Examination Date

A trial is generally conducted through hearing dates for oral argument.

At the first hearing date for oral argument, the parties appear, organize the issues, and state their positions.

Where the issues are complex or there is much dispute, the court organizes the case through ‘preparatory proceedings’ and then conducts witness examination, examination of the parties, and the like intensively on a ‘concentrated evidence examination date.’

Points to Note

∙ A party or representative must appear on the trial date
=> Failure to appear may lead to a judgment without oral argument or a judgment of loss

∙ Where a change of the date is necessary
=> An application to change the date must be submitted in advance, together with materials substantiating the grounds

Pronouncement and Finality of Judgment

Once the examination of evidence and oral argument are concluded, the court finally sets the date for pronouncement of judgment and discloses the result.

If no appeal is filed within two weeks after the judgment is pronounced, the judgment becomes final and acquires legal binding force.

Measures Available After the Judgment Becomes Final

▷ If the other party fails to pay the price, an application for compulsory execution may be filed

▷ Recovery through provisional attachment of real estate, attachment of claims, attachment of wages, etc.

The Procedure at a Glance

Name of Procedure

Summary of Key Content

Filing and Service of the Complaint

The plaintiff submits the complaint to the court

→ The complaint is served on the defendant

Submission of the Answer and Briefs

The defendant submits an answer to the complaint

→ Both sides organize their arguments in writing

Submission of Evidence and Examination of Evidence

Supporting evidence is submitted through documents, witnesses, etc.

→ The court admits the evidence

Hearing Date for Oral Argument and Concentrated Evidence Examination

Full trial proceedings are conducted based on both sides' arguments and evidence

Pronouncement and Finality of Judgment

The judge pronounces the judgment

→ If there is no appeal, it becomes final after two weeks

Compulsory Execution (if necessary)

If the other party fails to pay, the claim recovery procedure is conducted based on the written judgment

4. Construction Payment Lawsuit | Method of Compulsory Execution

Construction Payment Lawsuit How to Apply for Compulsory Execution Documents

Even if the plaintiff prevails in a construction payment lawsuit, if the other party does not voluntarily pay the money, the creditor must recover the price through a legal compulsory execution procedure based on the written judgment.

What Is Compulsory Execution

Compulsory execution is a procedure in which, based on a title of execution such as a final court judgment or a payment order, the debtor's property is compulsorily disposed of through state authority so that the creditor recovers the money.

Summary of Required Documents

Name of Document

Description

Authenticated Copy of the Title of Execution

Written judgment, protocol, notarial deed, etc.

Execution Clause

A certification that the court grants stating that execution is possible; an application is required

Certificate of Service

Proves that the written judgment was delivered to the other party

Certificate of Finality

A document proving that the judgment has become final

Resident Registration Number / Business Registration Number, etc.

Information identifying the parties to the execution is required (in the case of a corporation, the register / business registration certificate, etc.)

If the written judgment includes a declaration of provisional execution stating that provisional execution is possible, a certificate of finality need not be obtained.

5. Construction Payment Lawsuit | Checklist

Construction Payment Lawsuit Response Methods by Position of Contractor and Owner

In a construction payment lawsuit, the outcome may turn on the contractual relationship, the performance of the work, and whether evidence has been secured.


It is very important to check in advance the matters appropriate to one's own position before and after the lawsuit.

Contractor (Plaintiff) Response Checklist

▷ Are you keeping written contract materials such as the contract, estimate, and specifications?

▷ Have you organized the statement of work up to the point of completion or mid-term termination of the work?

▷ Do you have evidentiary materials such as photographs, text messages, and messenger conversations regarding the progress of the work?

▷ Is there a history of payment demands (requests for account transfer, certified mail, etc.)?

▷ Are the conditions for payment by degree of completion under the contract and the basis for calculating the amount clear?

▷ Have you reviewed whether the other party's (the owner's) grounds for nonpayment of the balance are reasonable?

▷ Have you ascertained the other party's address and property status? (in preparation for compulsory execution)

▷ Have you secured supporting documents that can be submitted to the court, such as settlement statements and tax invoices?

▷ Have you conducted your own check for defects in preparation for potential disputes over defects?

Owner (Defendant) Defense Checklist

▷ Are the contract terms clear, such as a written contract or a statement of agreed terms?

▷ Are there breaches of contract by the contractor (delay, defective construction, etc.)?

▷ Is there evidence of discrepancies between the work actually performed and the estimate or the contract content?

▷ Have you secured a history of requests for defect repair (text messages, email, messenger, etc.)?

▷ Is there a reason the work was halted before or during completion of construction?

▷ Are you preparing or have you secured a request for a defect appraisal or an appraiser's diagnosis report?

▷ Have you organized the amounts paid to the contractor and the details of progress payments, advance payments, and the balance?

▷ Have you secured on-site photographs, communication records, and statements that can be submitted to the court?

▷ If any payment has already been made, is there a receipt or account transfer record for it?

Construction Specialist Attorney Assistance System

This law firm includes a substantial number of construction specialist attorneys registered with the Korean Bar Association and specialist attorneys with an average of more than 10 years of experience.


Accordingly, comprehensive legal support is available, from determining whether the work has been completed, calculating progress payments, and assessing breach of contract and the existence of defects, to sending certified mail, filing a construction payment claim lawsuit, and carrying out compulsory execution.


If handling all of the procedures alone is difficult, we encourage you to proceed more accurately and promptly with the assistance of a construction specialist attorney.

Watch related video content
for this case study.

  1. What are the solutions and response strategies for compensation for construction defects?

Related Information
Background

Daeryun's Key Strengths

Daeryun's exclusive AI · IT
litigation strategies
Over 260
key members
1,200+ cases
handled monthly

* January 2026 Bar Association Transit Permit Issuance Criteria

*Complies with Korean Bar Association Advertising Regulations Article 4 Paragraph 1

Attorney
Legal consultation booking

All consultations are conducted by specialized lawyers after reviewing the case. It is carried out on a reservation basis to ensure a professional process.We encourage you to make an early reservation for consultation, and request adherence to the scheduled time. We will do our best to provide a satisfying consultation.

Phone
consultation 1800-7905

Available 24/7, 365 days
for consultation requests

Phone booking

KakaoTalk
consultation

KakaoTalk channel

Daeryun Law Firm Attorneys

KakaoTalk booking

Online
consultation

We provide tailored
legal services.

Online booking
Quick Menu

KakaoTalk